Greenwoods projects
Clubhouse roof restoration
Completed Started Jan 15, 2026Target Apr 30, 2026Completed Apr 22, 2026
Repaired the leaking roof deck and repainted the ceiling after the rainy season.
Overall progress100%
Budget ₱480,000.00
Spent ₱452,000.00
About this project
Completed
The roof membrane was replaced, gutters were cleared and the ceiling was repainted. A five-year workmanship warranty is on file at the office.
Project photos
Before, during and after photos from the project gallery.
No project photos have been published yet.